Illustrative modelFleet asset finance · Relevant to Fleet finance, FP&A

Engine shop-visit cost forecast

Maintenance cost for an engine fleet follows flight cycles, not the calendar. This build uses an invented fleet. Change utilization, the removal interval and escalation, and see when each engine is due, what each visit costs and the month the reserve runs short.

What this shows

  • Cycles to removal, visits per year and the month each visit lands
  • Cost per visit by workscope, with a vendor rate and yearly escalation
  • A reserve balance by month and the month it runs short
  • Scenarios for utilization, interval and escalation

How I use it

  • Forecasting maintenance cost from its drivers
  • Telling leadership when a reserve stops covering the plan
  • Testing how much a longer interval or a rate increase is worth

Explore the model below. It uses an invented company and invented numbers.

Explore the model

Illustrative model · Synthetic data

Wide tables scroll sideways: swipe inside a table to see every column.

Sample build: engine shop-visit forecast and reserve

Marlowe Peak Air is an invented airline with ten engines. Flight cycles decide when each engine comes off the wing. The workscope, the vendor's labor rate and a yearly price step decide what each shop visit costs. A maintenance reserve, paid in per flight cycle, covers the visits until the month it does not.

Synthetic inputs for illustration. Not data from any employer.

1,800
7,200
$200
4.0%
$4,000,000
$300
Workscope for every visit
Scenario

Running on 1,800 cycles per engine a year, a 7,200-cycle interval and 4% yearly escalation.

Shop visits in 36 months

7

2.5 a year once every engine is on its interval

Cost of those visits

$20.7M

$20,733,120, $2,961,874 a visit on average

Reserve runs short

Jan 2029

Month 25 of 36, the first negative balance

Lowest reserve balance

-$1.9M

-$1,883,120 in Sep 2029

What to try

  • Shorten the removal interval and watch engines already past it come due in the first month.
  • Raise the contribution per cycle until the run-short month disappears.
  • Switch the scenario to a longer interval and see how many visits slide out of the 36 months.
  • Pick an engine in the due dates tab to follow it from cycles to dollars.

When each engine comes off the wing

An engine is due when the cycles it has flown since its last shop visit reach the removal interval. Every engine flies 150 cycles a month at this utilization, so cycles to removal convert straight into months. After a visit the engine starts a fresh interval. At this pace the fleet makes 2.5 visits a year once every engine is on its interval.

E01E02E03E04E05E06E07E08E09E10Reserve runs short202720282029
LightHeavyFull restorationMonth the reserve runs short

Due dates, engine by engine

Cycles, months and the first removal for each engine. Pick an engine to follow it.
EngineWorkscopeCycles since last visitCycles to removalMonths to removalFirst removalVisits in 36 months
Heavy6,6006004Apr 20271
Light5,8001,4009.3Oct 20271
Full restoration5,0002,20014.7Mar 20281
Light4,3502,85019Jul 20281
Heavy3,4503,75025Jan 20291
Heavy2,6004,60030.7Jul 20291
Light2,3004,90032.7Sep 20291
Full restoration1,3505,85039Mar 2030 (after the forecast)0
Light7506,45043Jul 2030 (after the forecast)0
Heavy3006,90046Oct 2030 (after the forecast)0

Following E01

E01 has flown 6,600 cycles since its last visit. Against the 7,200-cycle interval, 600 cycles remain. At 150 cycles a month that is about 4 months, so the first removal lands in Apr 2027.

  • Apr 2027 (month 4): heavy workscope at $3,200,000, priced at the starting price list.

Base plan: 7 shop visits land in the next 36 months and cost $20,733,120. The reserve runs short in Jan 2029 (month 25) and bottoms at -$1,883,120 in Sep 2029. A contribution of $339 per cycle would keep it above zero.